RERA – Artifex.News https://artifex.news Stay Connected. Stay Informed. Thu, 06 Aug 2026 13:06:00 +0000 en-US hourly 1 https://wordpress.org/?v=7.1.3 https://artifex.news/wp-content/uploads/2026/05/cropped-cropped-app-logo-32x32.png RERA – Artifex.News https://artifex.news 32 32 With new SOP and software, revenue recovery in RERA cases expected to pick up pace https://artifex.news/article71309887-ecerand29/ Thu, 06 Aug 2026 13:06:00 +0000 https://artifex.news/article71309887-ecerand29/ Read More “With new SOP and software, revenue recovery in RERA cases expected to pick up pace” »

]]>

RERA-K has recently issued a circular on July 28 laying down a SOP for revenue recovery, a copy of which The Hindu has accessed.
| Photo Credit: File photo

Lax enforcement of revenue recovery orders issued by Real Estate Regulatory Authority – Karnataka (RERA-K) — only around 10% of the value of the Revenue Recovery Certificates (RRCs) have been recovered till date — has been a long-standing problem aired by homebuyers. A host of measures, including a Standard Operating Procedure (SOP) which empowers RERA-K to implement its orders, a dedicated officer and a software being developed to implement RRCs in Bengaluru, is expected to lead to better implementation of these orders. 

Operationalising Section 40(2)

RERA-K has recently issued a circular on July 28 laying down a SOP for revenue recovery, a copy of which The Hindu has accessed. The SOP operationalises Section 40(2) of RERA Act, 2016, which empowers RERA to enforce its orders “in the manner as if it were a decree or order made by the principal civil court of the original jurisdiction in a suit”, a provision on the books but almost never used. It is hoped that this will empower RERA-K implement its orders. 

M.S. Shankar, general secretary, Forum for People’s Collective Efforts, welcomed operationalising Section 40 enforcement of RERA orders in the circular, saying it will give more teeth to the Authority. “RRCs cannot remain passive requests sitting in administrative limbo. The Authority must routinely invoke its powers as a Principal Civil Court under Section 40(2) of RERA Act, 2016, to directly attach assets and compel compliance,” he said. 

Revenue Recovery Certificates (RRC) Count Value
RRC issued  2,556 ₹1,214.32 crore 
RRC recovered  329 ₹123.84 crore 
RRC pending  2,227 ₹1,090.48 crore 

SOP 

Sixty days after passing of an order by the Authority, it shall verify compliance by sending communication to both the builder and the homebuyer. In case of failure of the builder to fully comply with the order, the complainant homebuyer has to file a petition on the RERA-K portal seeking enforcement of the RRC. Following this, the builder will be given two weeks’ time to comply with the order or file its response and will again be given two weeks time to comply. 

If the builder still fails to comply, the builder will be directed to file an affidavit disclosing and detailing all its moveable and immoveable assets, including bank accounts and other investments, within a period of two weeks. The complainant/homebuyer will also be given an opportunity to submit assets of the builder known to them. In case of non-compliance even at this stage, RRC will be prepared and forwarded for attaching and auctioning of the moveable and immoveable properties, including bank accounts. 

If the builder fails to comply the order for non-monetary reliefs covered under Section 40 (2) of the RERA Act, 2016, the Authority may either enforce the order as if it were a decree or order made by a principal civil court in a suit, or transmit the order to the Principal Civil Court having jurisdiction over the builder. 

Dedicated officer, software 

The State government has recently made Jayamadhava P., Special Deputy Commissioner, Bengaluru Urban District, in-charge of implementation of RRCs in Bengaluru, the district with the highest number of RRCs. “We are streamlining the process of implementation of RRCs, including developing a dedicated software and a portal for the same. This will remove inordinate delays and ensure they are implemented within the 3.5 months’ time needed to implement any RRC, giving due time to the builders to respond and comply as per the rules. This will bring in more transparency and help the complainant homebuyer to also follow up on the process of implementation of RRCs,” he said. 



Source link

]]>
CREDAI Mysuru to hold RERA awareness workshop https://artifex.news/article70270347-ecerand29/ Wed, 12 Nov 2025 12:39:00 +0000 https://artifex.news/article70270347-ecerand29/ Read More “CREDAI Mysuru to hold RERA awareness workshop” »

]]>

The Confederation of Real Estate Developers’ Association of India’s (CREDAI) Mysuru chapter will be organising a Real Estate Regulatory Authority (RERA) workshop in the city on December 6, 2025.

A statement issued in Mysuru on behalf of CREDAI, Mysuru, said the RERA workshop seeks to create awareness among developers of residential layouts, builders, and other stakeholders in the real estate sector.

Senior officials from Karnataka RERA, Bengaluru, will participate in the workshop which will be held at Mysuru Builders’ Charitable Trust (MBCT) Hall in Vishveshwaranagar in the city.

The workshop is expected to throw light on the latest rules in the real estate sector, compliance procedures, and practical aspects of the RERA Act.

According to CREDAI, Mysuru, senior officials from Karnataka RERA, Bengaluru, will participate in the event and provide guidance on the registration process for ongoing and new projects under RERA, project extensions, and compliance measures, besides creating awareness about customer grievance redressal procedures and common challenges faced by builders and the possible solutions.

CREDAI, Mysuru, has been working to promote transparency and accountability in the implementation of the RERA law, the statement said, before adding that the programme will provide an interactive platform for builders and developers to engage directly with RERA officials and get answers to their queries.

The programme is scheduled to begin at 4.30 p.m. on December 6 at the MBCT Hall and interested persons can contact mobile number ‘9945147472’.